ROCHESTER, Minn. (KTTC) -- Crews energized the first of two 161 kV transmission lines for the Hampton-Rochester-La Crosse part of the CapX2020 transmission project on Thursday.

The 161 kV line goes from the new north Rochester substation to RPU’s Northern Hills substation. Another 161 kV line is scheduled to go in-service to the east of Rochester in 2015.

"When complete, the Rochester area will have added redundancy in its transmission infrastructure providing for added security and reliability," said RPU Communications Coordinator Tony Benson.

Completion of the Rochester-Hampton-La Crosse transmission line project is scheduled for late 2015.



Most Viewed Content

Stories
Videos

What's on WXOW tonight

Powered by WorldNow
All content © Copyright 2000 - 2014 WorldNow and WXOW. All Rights Reserved.
For more information on this site, please read our Privacy Policy, Terms of Service and Mobile Privacy Policy & Terms of Service.

Persons with disabilities who need assistance with issues relating to the content of this station's public inspection file should contact Administrative Assistant Theresa Wopat at 507-895-9969. Questions or concerns relating to the accessibility of the FCC's online public file system should be directed to the FCC at 888-225-5322, at 888-835-5322 (TTY) or at fccinfo@fcc.gov.